Affordable housing delivery strategy 2021 to 2023
This review provides an update on the outcomes achieved through the implementation of the actions set out in this strategy.
The Affordable housing delivery strategy is a sub-strategy of the Housing strategy 2021-2023; one of the priorities of the Housing strategy is developing new council homes.
In addition to the below outcomes, the Development Team have also been crowned as Leader’s Team of the Year 2023 and have been shortlisted in the Development Strategy of the Year category at the EEM Building Communities Awards 2023.
2021 to 2023 Actions
Actions | Update | Status |
---|---|---|
Deliver 100 new affordable homes by 2025 | 108 new affordable homes completed or on site as at February 202330 homes have been acquired from the market, including s.106 properties | Complete |
Continue to form partnerships with registered providers as required to deliver new affordable homes | Froghopper Lane scheme developed in partnership with emh group | Complete |
Continue to maintain a register of sites in need of regeneration that could deliver additional homes | All other council development sites are being delivered directly by ADC. All council owned sites have been assessed for either development or disposal. | Complete |
Continue to maximise the delivery of adapted homes on Council led or enabled developments | The Development Team proactively monitor the market for opportunities 7 adapted homes have been delivered in 2021 - 2023 | Complete |
Explore all available opportunities to acquire properties and sites, including other public sector estate, regeneration opportunities, auction and private sale opportunities, s.106 properties. | 30 homes have been acquired from the market, including 25 s.106 properties and 4 Right To Buy buy-backs Negotiations are in progress to acquire land from the open market | Complete |
Conclude the disposal options appraisal for Council owned land at Diamond Avenue and Clegg Hill | Appraisals completed | Complete |
Complete the disposal of un-viable garage sites to release capital for reinvestment | Sale of first 4 sites completed - other sites are under discussion. | In progress |
Identify Council community centres suitable for regeneration to provide new affordable homes | 2 centres have been redeveloped to provide 4 bungalows | Complete |
As part of the Towns Fund and Future High Streets Fund Project, lead on any opportunities to deliver affordable housing | No opportunities identified to date | Complete |
Ensure all commuted sums are utilised within the required timescales | All commuted sums available in 2021-2023 have been utilised | Complete |
Implement the recent national policy changes to the use of Right to Buy receipts | Policies and procedures have been amended as required | Complete |
Update the specification for new build homes delivered by the Council to minimise carbon emissions (current minimum standard set is EPC B or better) | Specifications are developed site by site and are subject to financial viability. A fabric first approach is adopted in all cases and wherever possible, minimum standards are exceeded. | Complete |
Monitor supply and demand in the affordable home ownership and s.106 markets, and work with Planning to address any challenges | 47 s.106 social/affordable rented homes delivered by the market in 2021-2023, of which ADC acquired 25. No issues with supply or demand of affordable home ownership products identified. |
Complete |
Explore procurement opportunities to improve the value for money and quality of services provided by professional service partners such as architects, quantity surveyors, etc. | A number of professional service partners are now in place providing good value for money and high quality services. | Complete |
Explore procurement opportunities to improve the social value outcomes of development projects | Procurement is via framework agreements – social value outcomes are prescribed by the procurement consortiums | Complete |
Explore procurement opportunities to minimise carbon emissions from development projects | Opportunities are explored on a case by case basis, such as using sustainable materials, mixing mortar on site and off-site construction of roof trusses | Complete |
2023 to 2025 actions
- Deliver 100 new affordable homes between 2023 - 2028
- Continue to maximise the delivery of adapted homes on Council led or enabled developments
- Explore all available opportunities to acquire properties and sites, including other public sector estate, regeneration opportunities, auction and private sale opportunities, s.106 properties
- As part of the Towns Fund and Future High Streets Fund Project, lead on any opportunities to deliver affordable housing
- Ensure all commuted sums are utilised within the required timescales
- Explore opportunities to increase the supply of Extra Care housing in Ashfield
- Explore opportunities to deliver homes that achieve the highest standards of energy efficiency, such as Passivhaus
- Explore opportunities resulting from the East Midlands Mayoral Authority (launching May 2024)
- Maximise the delivery of affordable housing by Registered Provider partners
- Revise policies and procedures as required by the Social Housing (Regulation) Act
- Identify opportunities to maximise affordable housing delivery as a result of proposed planning policy reforms
- Monitor customer satisfaction with new homes to identify opportunities for improvement
- Monitor ongoing quality of new homes by reviewing data (such as defect reports, repairs requests, stock condition surveys) to identify opportunities for improvement